Don Valley Case Studies

Don Valley Engineering are proud to deliver value added projects to many of our returning customers world wide, providing them with a great return of investment.

We also welcome the opportunity to work with new customers, so they too can realise these value added benefits.

See our most recent projects below:


Project:

FGD Reception Facility

Location:

Bristol

Value:

£

Client:

EXTEX Siniat

Date:

July 2014

Project Overview:

Design Supply of new FGD truck Unloading system, designed to receive 10 trucks per hour. Material delivered by Rail is offloaded into Trucks and delivered to the Bulk Reception Unloader, Where the FGD is discharged on to the Apron Belt and transferred to a tripper conveyor feeding a bulk store. Don Valley Engineering in conjunction with sister company Cleeve MH provided the design Supply and Mechanical Erection of the plant and equipment.


Project:

Ash Returns System

Location:

DRAX Power

Value:

£650k

Client:

LYTAG Aggregates

Date:

September 2014

Project Overview:

Design Supply of new Pneumatic conveying system to return filtered PFA dust from the process area back to the PFA feed supply line.The project involved the design and supply of a new Dense phase conveying system, Bulk storage a silos and hoppers, Mechanical erection of the Don valley Engineering equipment and 3rd party plant supply. Including all site supervision.


Project:

Carbon Mixing

Location:

Bawtry, Doncaster

Value:

£1.2m

Client:

Thomason's Leeds

Date:

October 2014

Project Overview:

Rebuild of a Mixing Tower, for Bawtry Carbon International following severe fire damage. Don Valley Engineering limited appointed CDM Principal Contractor by Thomason’s main contractor for the project. Don Valley Engineering oversaw all site supervision for the execution of the Mechanical & Electrical installation work and construction phase of the project. The project involved site management of a multi-disciplined work force made up of European companies The project was delivered to budget and ahead of the project program.


Project:

Fuel Blending Plant

Location:

Ferrybridge

Value:

£2.6m

Client:

Keadby Generation

Date:

October 2013

Project Overview:

For the blending of raw coal to feed the Power Stations fossil fuel feed system The principle behind the project was to enable the client to mix and blend coal from a stock pile of over 3m tonnes with new coal,being brought in by rail. The client requested that the DVE system would have to be capable to feed material at 800tph as a back-up route to the station in case the rail system was disabled in any way. The project was successfully delivered to the agreed program and budget.

Call Us NOW!
We can help you.

Monday – Friday
8.30am – 5.00pm

01302 272703

Not a fan of the
phone?

Don’t worry, you can
contact us by email

Click here!

Click here to download
our brochures

To find out more why
not read our brochures

Click here!

What our customers say