7th November
2005
Initial Site Set Out |
|
16th November
2005
Civil Works Start |
|
20th November
2005
Steel Erection on Office Block |
 |
|
 |
|
 |
12th December
2005
Steel Erection Starts on Workshop Facility |
|
16th December
2005
Steel Erection Continues on Workshop Facility |
|
16th December
2005
Steel Erection Continues on Workshop Facility |
 |
|
 |
|
 |
16th December
2005
Barry Smith, Don Atkinson & Stuart Harrison Inspect Site Progress |
|
16th December
2005
Blockwork Starts on Office Block |
|
15th January
2006
Brickwork Progresses |
 |
|
 |
|
 |
19th January
2006
Structual Steelwork of the Works Nears Completion |
|
19th January
2006
Structual Steelwork of the Works Nears Completion |
|
30th January
2006
Floor Slab in Office Completed |
 |
|
 |
|
|
30th January
2006
Preparations For Floor Slab |
|
3rd February
2006
Roof Sheeting Progresses |
|
|